Foundations:

Basement Footings

8" X 18" concrete with #4 Rerod

Walls

10" poured concrete walls with #4 Rerod

Garage Footings

8" X 14" concrete

Garage Walls

6" poured concrete filled level with compacted sand to grade or 8" block with 4" top course

Damp Proofing

Bituminous spray coating

Footing Drains

4" perforated plastic (inside and outside) with pea pebble covering

Columns

3" steel adjustable with 15,000 pound load capacity

Beam

Steel "I" beam sized for load requirements

Backfill

Sand to within approximately 18" of grade

Return to top

Framing:

Floor

2" X 10" joists, TJI, or engineered floor trusses, 3/4" T & G OSB underlayment (glued and nailed)

Exterior Walls

2 X 4 studs, 16" OC

Interior Walls

2 X 4 studs, 16" OC

Garage Walls

2 X 4 studs, 16" OC

Return to top

Roof:

Roof Trusses

2 X 4 trusses, 24" OC

Sheathing

7/16" OSB with ply-clips

Shingles

Elk raised profilewith 30 year warranty

Return to top

Exterior Finishes:

Siding

Vinyl siding, 4/4 simulated wood grain, Wolverine Benchmark 44

Soffit

Aluminum or vinyl

Fascia

Wrapped in aluminum

Windows

Jeld-Wen builder clad-wood casement with aluminum cladding, 3/4" insulated, Low-E, argon-filled glass; full screens on operating units

Gutters & Downspouts

Seamless aluminum

Return to top

Exterior Doors:

Entry Doors

Peachtree Insulated steel door, 1-3/4" thick polyurethane core, with key-in-knob Surelock doorknob and Surelock deadbolt

Garage

16' X 7' Insulated steel, 4-panel flush overhead door

Return to top

Insulation:

Walls

3-5/8" fiberglass (R-13) with vapor barrier; wrapped with Tyvek

Ceiling

10" cellulose (R-38) in flat ceilings; 12" fiberglass (R-38) in cathedral ceilings

Basement

3-5/8" fiberglass (R-13) at bond

Return to top

Interior Finishes:

Trim

OG style clear pine base and casing, stained and varnished

Walls and Ceilings

1/2" drywall primed and painted; textured cathedral ceiling (where applicable)

Fire Wall

5/8" drywall (primed)

Doors

1-3/8" flush, hollow core oak veneer with pine veneer jambs, or six-panel masonite

Stairs

Pine treads and risers

Hardware

Surelock polished brass; bathroom & master bedroom privacy sets

Return to top

Concrete Flatwork:

Basement

4" concrete on compacted sand fill with vapor barrier

Garage

4" concrete on compacted sand fill with #3 rerod, 48" OC each way

Return to top

Floor Covering Allowance:

 

Per plan, using stain resistant carpet (one color throughout), laid over 6# rebonded pad.

Kitchen, Laundry and Baths: Vinyl, laid over 1/4" underlayment.

Foyer: 3/4" wood plank, 10 year wear and finish warranty, lifetime structural integrity warranty.

Return to top

Kitchen Allowance:

 

Per plan, using oak "Spring Valley Oak" series by Merillat; plastic laminated countertops in kitchen & baths.

Return to top

Appliance Allowance:

 

$635 (includes HDA 3400 Hotpoint dishwasher, Broan 4130 ductless range hood, RB 757 Hotpoint self-cleaning electric range)

Return to top

Electrical Service (underground):

Panel

150 amp

Wire

Romex

Openings

To code; front and rear exterior weatherproof outlets; overhead garage door outlet

Special Outlets and Circuits

Disposal, laundry, furnace, dishwasher, interlocked smoke detectors (per code), chime wiring, future ceiling fan (in cathedral), GFI bath, kitchen and garage circuits, and outlet for water softener

Telephone

Two openings (RG6)

Cable TV Pre-Wire

Two openings, Cat 5E

Lighting Fixtures

Choice of preselected packages

Return to top

Heating:

Furnace

Tappan forced air gas furnace or equal, minimum 100,000 BTU (80% A.F.U.E. rating), prepped for air conditioning

Duct Work

Galvanized sheet metal with negative pressure inlet

Controls

7-day programmable thermostat

Return to top

Plumbing:

Water Piping

Copper

Waste Drains

PVC

Water Heater

A.O. Smith 40-gallon gas FSG 50 or equal, 40,000 BTU (recovery rate of 37.7 gallons per hour)

Water Closet

Mansfield 135-160 of vitreous china

Bath Sink

Mansfield 19" X 16" SRO of vitreous china

Tub and Shower Unit

MAAX AKER CM-60 fiberglass tub; MAAX AKER SHLS-48 fiberglass shower

Kitchen Sink/Faucet

Dayton 3322 stainless steel sink; Moen 67425 faucet

Bath Faucets

Moen L2353 for tub; Moen L2352 for shower; Moen L4621 for lav

Disposal

Badger I by Insinkerator

General

Front and rear exterior hose bibs, water softener bypass, laundry (per plan) with Guy Gray box OR laundry tub

Return to top

Driveway:

 

Concrete

Return to top

Landscaping:

 

Optional

Return to top

Utilities:

Water/Sewer

Village of Dexter

Electric

DTE Energy

Cable TV

Comcast

Gas

DTE Energy

Telephone

SBC Ameritech

Return to top

Allowances:

Subject to verification at time sales agreement is signed

   

Note:

Plans, specifications & prices are subject to change without notice.